Corran Ferry Infrastructure Improvement Scheme
We have included some information from the Highland Council below regarding the renovation to the Corran Ferry Infrastructure, and any community meetings associated with this.
Photo Credit: Steve Pearse
Public Notices
Up to date information can be found directly via the Highland Council Website, however we will endeavour to share any updates we receive, below.
March 2026
Corran Ferry Infrastructure – Community Liaison Meetings
Following the first community meeting, it was agreed that Community Liaison Meetings will now take place on the third Wednesday of each month for the foreseeable future.
Meetings will alternate between Ardgour and Nether Lochaber, although residents are welcome to attend whichever location is most convenient.
The next meeting will take place in Ardgour Memorial Hall on Wednesday 18th March.
Minutes for the previous meeting can be obtained by emailing Ardgour Community Council secretary.ardgourcc@gmail.com
February 2026
A82 Corran Ferry - Northbound lane closure from 16 February
Traffic management will be in place on the A82 trunk road, just north of the Corran Ferry junction, from 16 February 2026 to support essential works linked to the Corran Ferry Infrastructure Improvement Scheme.
Works will take place in two phases:
Phase 1: 16 February to 6 March 2026
Tree clearing works
Northbound lane closure
Daytime hours only
After this phase, there will be a two week pause with no road restrictions.
Phase 2: 23 March – 24 April 2026
Construction of the new junction for the Corran Ferry Infrastructure Improvement Scheme.
Northbound lane closure
Daytime hours only
The Highland Council will continue to provide updates as works progress, please keep an eye on their social media pages.